Gatwick Diamond, South east Coast Ambulance Emergency Call Centre | Crawley | West Sussex

CLIENT Willmott Dixon

LOCATION Crawley, West Sussex, RH10 9XN

DURATION 2016

  • To develop a new Emergency Operations Centre (EOC) in West Sussex (Gatwick) replacing two existing EOCs.

  • VZDV became involved during design stages 3 & 4, to provide specialist design services that ensured the overall design requirements of a resilient infrastructure were met.

  • To ensure the service strategy aligned with SECAmb vision and met the requirements for Surrey County Council.

  • In this instance, the project had a number of challenges in terms of service strategy, lack of resilience and building dimensions which needed to be adapted to meet the overall building and user requirements.

In proud collaboration with:

Surrey County Council, South East Coast Ambulance Service (SECAmb) & Willmott Dixon Construction Limited


BACKGROUND

Due to increasing demand (25% each year for 4 years) for emergency ambulance services to the SECAmb 999 call centres, SECAmb has identified the need for a new Emergency Operations Centre (EOC) in West Sussex (Gatwick) which will replace two existing EOCs. This will entail 70 EOC staff working on a 24-hour rota 7 days a week.

The EOC is to handle 70% of SECAmb’s total EOC activities at any one point in time. In addition, it will require ICT and power/space resilience capabilities to handle 100% of SECAmb’s overall EOC activities. In the event of failure at its second EOC (located in Kent), the new Gatwick EOC will manage 100% of SECAmb’s EOC responsibilities and vice versa for the future of Kent EOC. This, therefore, means that the new building infrastructure will need to support this level of potential use.

THE OBJECTIVE

As a strategic design partner for Willmott Dixon VZDV became involved during design stages 3 & 4, to provide specialist design services to ensure the service strategy aligned with SECAmb vision and met the requirements for Surrey County Council.

 

THE CHALLENGE

VZDV were charged with ensuring that the overall design requirements of a resilient infrastructure were met. The services design was critical in ensuring that any single point of failure was minimised and that the building services were designed so that operation and maintenance of the services did not affect the 24/7/365 operation of the building. SECAmb had a preference for low velocity underfloor displacement ventilation.

THE DEFINING MOMENT

SECAmb had a strong preference for using displacement ventilation with chilled beams as a service strategy. However, the building was not designed for displacement ventilation in terms of floor-to-floor heights, riser space and locations and roof plant space allocation, and as a result, the proposed service strategy would not meet SECAmb performance criteria.

VZDV investigated this further with the assistance of computational fluid dynamics (CFD) analysis and provided further options as a ventilation strategy. The final outcome was the use of overhead variable air volume (VAV) ventilation system which was suitable for the building and application and met the required performance criteria. In addition this form of ventilation had the following benefits:

  • Reduced floor-to-floor dimensions

  • Reduced on floor maintenance

  • Low background noise

  • Dedicated plant and risers providing resilience

  • Allowed free cooling in shoulder months   

THE TRANSFORMATION

From a services perspective, the key stage of the design was advising the Client the requirements for resilient services which entailed:

  • Tier 2 electrical infrastructure

  • N+1 generator configuration

  • UPS in N+1 configuration

  • N+1 heating and cooling infrastructure

  • N+1 ventilation systems

  • Security systems (CCTV, access control, fire alarms)

  • Audio visual systems

  • Resilient IT infrastructure

  • BMS

In addition, the building was to incorporate a number of sustainable and energy-efficient features:

  • BREEAM rating

  • Enhanced thermal envelope

LEARNINGS

This project demonstrated that with the right design and procurement team in place, almost any challenge can be overcome. In this instance, the project had a number of challenges in terms of service strategy, lack of resilience and building dimensions which needed to be adapted to meet the overall building and user requirements.

Credit to the HGP Architects, LON Structural Engineers, SECAmb, Surrey County Council and Willmott Dixon for providing the support and knowledge to make the changes necessary to the scheme for a successful outcome.

NEXT STEPS

We are seeking local authorities looking to develop similar energy and emergency facilities.

Van Zyl & de Villiers (VZDV)

GET IN TOUCH

 

 

MORE VZDV PROJECTS

 
 
Previous
Previous

Chiswick Health Centre | London | W4

Next
Next

New Ladderswood Regeneration Residential Development | London | N11